Who establishes the Substantial Completion date?

Owner

Contractor

Architect/Engineer

Substantial completion is the point in time when the work is considered sufficiently complete for the owner to occupy or use it for its intended purpose under the contract. The Architect/Engineer, acting as the contract administrator, certifies this milestone. After a final inspection with the contractor and owner, the Architect/Engineer issues a certificate of substantial completion, and the date on that certificate becomes the Substantial Completion date. The owner, contractor, or surety do not unilaterally establish this date—the certification authority rests with the Architect/Engineer based on the contract documents. This certification also typically triggers certain warranty periods and shifts certain responsibilities, such as punch-list completion and insurance considerations, as outlined in the contract.

Surety

Want more questions?

All options are one-time payments.

$12.99

30 day pass for new members

All the basics to get you started

  • Ad-free experience
  • View your previous attempt history
  • Mobile app access
  • In-depth explanations
  • 30 day premium pass access
$29.99 $92.93 usd

6 month DELUXE pass (most popular)

Everything with the 30 day premium pass FOR 6 MONTHS! & the ultimate digital PDF study guide (BONUS)

  • Everything included in the premium pass
  • $92.93 usd value for $29.99! You save $62.94!
  • + Access to the ultimate digital PDF study guide
  • + 6 months of premium pass access
  • + Priority support
$14.99 $19.99

Ultimate digital PDF study guide

For those that prefer a more traditional form of learning

  • Available for instant download
  • Available offline
  • Hundreds of practice multiple choice questions
  • Comprehensive content
  • Detailed explanations
Image Description
Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy