Which document is typically used to provide a cost breakdown by value and is prepared by the Contractor?

Study for the CSI Construction Documents Technology (CDT) Exam. Learn with flashcards and multiple choice questions, each question has hints and detailed explanations. Get ready to ace your exam!

Multiple Choice

Which document is typically used to provide a cost breakdown by value and is prepared by the Contractor?

Explanation:
The Schedule of Values is the document that provides a cost breakdown by value and is prepared by the contractor. It breaks the contract sum into discrete, value-based line items—often aligned with divisions or major work elements—each with an estimated cost and a running total. This format lets progress payments reflect the value of work completed and provides a clear reference for tracking changes, substitutions, and budget changes as the project advances. The other options serve different purposes: a notice of defect communicates deficiencies; items furnished by the owner refers to owner-provided materials or services; and “resource drawings” isn’t a standard cost-tracking document in CDT practice.

The Schedule of Values is the document that provides a cost breakdown by value and is prepared by the contractor. It breaks the contract sum into discrete, value-based line items—often aligned with divisions or major work elements—each with an estimated cost and a running total. This format lets progress payments reflect the value of work completed and provides a clear reference for tracking changes, substitutions, and budget changes as the project advances. The other options serve different purposes: a notice of defect communicates deficiencies; items furnished by the owner refers to owner-provided materials or services; and “resource drawings” isn’t a standard cost-tracking document in CDT practice.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy