Minor Changes in Work

Study for the CSI Construction Documents Technology (CDT) Exam. Learn with flashcards and multiple choice questions, each question has hints and detailed explanations. Get ready to ace your exam!

Multiple Choice

Minor Changes in Work

Explanation:
Minor Changes in Work are written instructions issued to the contractor that clarify or interpret the contract documents but do not change the contract sum or contract time. This concept is about making small, non-costly, non-schedule-impact adjustments that keep the project moving without requiring formal changes to price or schedule. The correct option describes exactly that: a written instruction or interpretation that does not involve any adjustment to cost or time. In practice, you might see a minor change when a drawing ambiguity is resolved or a small substitution is allowed without affecting the overall price or construction timeline. If an instruction would alter the amount due or extend the schedule, it would fall outside Minor Changes in Work and would typically be handled as a Change Order (for price) or a Construction Change Directive that includes time implications. A change in scope requiring a new permit clearly goes beyond the scope of a Minor Change in Work.

Minor Changes in Work are written instructions issued to the contractor that clarify or interpret the contract documents but do not change the contract sum or contract time. This concept is about making small, non-costly, non-schedule-impact adjustments that keep the project moving without requiring formal changes to price or schedule. The correct option describes exactly that: a written instruction or interpretation that does not involve any adjustment to cost or time.

In practice, you might see a minor change when a drawing ambiguity is resolved or a small substitution is allowed without affecting the overall price or construction timeline. If an instruction would alter the amount due or extend the schedule, it would fall outside Minor Changes in Work and would typically be handled as a Change Order (for price) or a Construction Change Directive that includes time implications. A change in scope requiring a new permit clearly goes beyond the scope of a Minor Change in Work.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy