Change Order is

Study for the CSI Construction Documents Technology (CDT) Exam. Learn with flashcards and multiple choice questions, each question has hints and detailed explanations. Get ready to ace your exam!

Multiple Choice

Change Order is

Explanation:
Change orders are written instructions that authorize addition, deletion, or revision in work, contract sum, or contract time. They formalize a change in the project scope that affects price or schedule and become part of the contract documents once signed by the relevant parties. A phone call is informal and lacks the written documentation needed to modify the agreement. A budget line item is simply a cost category, not a contract change. A shop drawing is a submittal showing how the contractor will perform the work and does not modify the contract itself.

Change orders are written instructions that authorize addition, deletion, or revision in work, contract sum, or contract time. They formalize a change in the project scope that affects price or schedule and become part of the contract documents once signed by the relevant parties. A phone call is informal and lacks the written documentation needed to modify the agreement. A budget line item is simply a cost category, not a contract change. A shop drawing is a submittal showing how the contractor will perform the work and does not modify the contract itself.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy