A contractor claim arises when conditions are what?

Study for the CSI Construction Documents Technology (CDT) Exam. Learn with flashcards and multiple choice questions, each question has hints and detailed explanations. Get ready to ace your exam!

Multiple Choice

A contractor claim arises when conditions are what?

Explanation:
A contractor claim typically arises when actual site conditions differ from what the contract documents indicate or show. The documents set the expected conditions for work; if what is found on site is materially different, the contractor may seek extra time or money to cover the added effort, costs, or risks. This situation is known as differing site conditions, specifically when the real conditions are contrary to what was indicated in the contract documents. Weather delays or owner change orders can lead to claims as well, but they come from different triggers than conditions that contradict the contract drawings or specifications, and aligning with the contract documents wouldn’t prompt a claim since it reflects what was assumed in the contract.

A contractor claim typically arises when actual site conditions differ from what the contract documents indicate or show. The documents set the expected conditions for work; if what is found on site is materially different, the contractor may seek extra time or money to cover the added effort, costs, or risks. This situation is known as differing site conditions, specifically when the real conditions are contrary to what was indicated in the contract documents. Weather delays or owner change orders can lead to claims as well, but they come from different triggers than conditions that contradict the contract drawings or specifications, and aligning with the contract documents wouldn’t prompt a claim since it reflects what was assumed in the contract.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy